2023 November 2nd Week KYOCM News Recommendation -Super grid transformers delivered

2.png

Located at GE’s Stafford engineering facility, the two 5 metre high, 215 Tonne transformers measured 8 metres long by 4 metres wide and required a transport solution to Aberdeenshire, Scotland.

Delivering each of the transformers on separate occasions, Collett mobilised their 250 Tonne capacity Goldhofer girder bridge in modular form, arriving in Stafford to configure the trailer and load the first of the cargoes.  Once loaded, the transformer and girder bridge combination featured a 65.8 metre overall length, with a rigid length of 41.6 metres.  This required extensive surveying and route planning ahead of the first leg of the project, transporting the cargo from Stafford to Ellesmere Port.

Having undertaken route access surveys, visual route inspections and numerous swept path analysis reports, the Collett Team identified several modifications and traffic management procedures to allow the cargo to safely navigate the route from the point of origin to the port.  This included extensive street furniture removal (including electrical elements), tree trimming, parking restrictions and designated hold points to allow the continual flow of traffic.  

With all this in place the Collett Team began the project.  

Departing from the Stafford facility, Collett travelled 70 miles over two days, with a total of 11 hours travelling time.  Undertaking contraflow manoeuvres at several highlighted pinch points along the way, the Collett Team travelled from Stafford, via Stoke-on-Trent and Congleton, before heading west towards Chester and final onward arrival at Ellesmere Port.

At the port Collett were welcomed by an awaiting Leibherr LG1550 mobile crane.  Here, working under CPA Contract Lift Conditions, the Collett Heavy Lift Team unloaded the 215 Tonne super grid transformer from the girder bridge.  Having undertaken all ship’s chartering operations, the transformer was loaded directly to a coaster vessel for onward shipment to the Port of Aberdeen.  With the cargo safely lashed and secured on board the vessel, the coaster set sail for Aberdeen whilst Collett dismantled the girder bridge trailer.  Then, travelling once again in modular form, the Collett Team transported the trailer via road to greet the incoming vessel and transformer at the Port of Aberdeen.

Arriving three days later in Scotland, the 215 Tonne transformer was discharged from the vessel by a 600 Tonne strut crane directly to the girder bridge trailer for the final leg of the journey.  With the final 14 miles having also been extensively surveyed in the planning stages of the project, all street furniture and route modifications had already been completed.  This also included the relocation of a post box and the widening of site access roads to allow the 4.2 metre loaded combination to access the site.  With all this in place, the 65m long loaded girder bridge arrived on site at the 400kV substation extension site at Leylodge, Kintore.

Once unloaded on site, and having undertaken detailed ground bearing and pressure calculations, the Collett Team began jacking and skidding operations to position the cargo.  Utilising their specialist hydraulic equipment, Collett were able to jack and skid the super grid transformer, accurately monitoring force and pressure during the operation, including forces on the jacks, on each skid shoe and maximum ground pressures throughout.

All this combined allowed Collett to safely and successfully deliver the first of the two 215 Tonne super grid transformers, returning to GE Stafford’s facility in the coming weeks to begin the operation to deliver the second.  Following the same procedure, the Collett Team loaded, transported, shipped and positioned the second of the transformers, completing the Kintore substation extension project.


(https://www.engineerlive.com)


More About KYOCM:

Located in industrial area of the Zhaozhuang Industry Park in Linqing, Shandong, Kaiyou Bearings Co., Ltd. is a professional bearing manufacturer and exporter with nearly 20-year experience. The products have reached the international advanced level with advanced production technology and modernized measuring management. Products are widely used in electrical and mechanical trades, the farm machinery industry, the automobile industry and all kinds of transmission facility manufacturing extensively. The products have a good sale in domestic and international dozens of country or region. Companies with the “integrity-based, quality firs” as the operational concept.

 

2023 New Week Hot Products Recommended:

Slewing Bearing :

Rotary bearings consist of an inner ring and an outer ring, one of which usually contains a gear. Together with the connecting holes in the two rings, they enable optimized power transmission through simple and fast connections between adjacent machine parts. Bearing raceways are designed with rolling elements, cages or gaskets to accommodate loads acting individually or in combination in any direction.

Features and advantages:

High carrying capacity

High stiffness for rigid bearing applications

Low friction

Long service life

Surface protection and corrosion resistance

Integrate other features including:

Driving mechanism

Control device

Lubrication system

Monitoring system

Sealed cassette tape

https://www.kyocm.com/products/Slewing-Bearing/745.html

 

图片1.png

 

For dimensions and specifications, contact us now:

Add: No.57 Youzhuang Commerial Street Zhaozhuang industry Garden Linqing City Shandong China

Tel: 0086-635-2632030

Fax: 0086-635-2632918

Email: yobearing@hotmail.com

Web: www.kyocm.com


2023-11-08

Hoziroq boshlang

Men harakat qilaman:

Contact